Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- STREETSCAPE IMPROVEMENTS AT MAIN STREET & MAYWOOD STREET
The project involves pedestrian access and streetscape improvements on local roadways in the Main South section of Worcester around Clark University. Intersection and Traffic signal improvements will be made at the intersection of Main Street at Maywood Street.
Location:
  • City of Worcester
  • Construction Begins: Autumn 2018
    Resident Engineer: Jonathan Viner
    Construction Bid Price: $1,793,214.50
    District: District 3

    Contracts (1) Progress
    # 102880 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Main and Adjacent Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/12/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/07/2009
    Project Initiation Form PIF Entered 05/21/2012
    Project Initiation Form PRC Submitted 11/08/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 12/02/2017
    Project Management
    100% Design 100% Package Received 12/06/2016
    100% Design 100% Package Comments to DE 01/23/2017
    25% Design 25% Package Received 03/05/2015
    25% Design 25% Package Comments to DE 06/11/2015
    25% Design 25% Package Received - Resub 1 05/03/2016
    25% Design Design Public Hearing 07/19/2016
    Final Design PS&E Received 08/24/2017
    Final Design PS&E to Peer Reviewer 08/24/2017
    Final Design Peer Review Comments to DE 09/07/2017
    Final Design PS&E Received - Resub 1 11/16/2017