Project Description:
ARLINGTON- BELMONT- CAMBRIDGE- LEXINGTON- LINCOLN- SIGN REPLACEMENT & IMPROVEMENTS ON STATE ROUTE 2
This project will replace and update all overhead and ground mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the State Route 2 mainline and intersecting secondary roadways from the Bedford Road intersection in Lincoln easterly to the Route 3/Route 16 intersection in Cambridge.
Location:
  • Town of Arlington
  • Town of Belmont
  • City of Cambridge
  • Town of Lexington
  • Town of Lincoln
  • Resident Engineer: Michael McGeoch
    Construction Contract Value: $2,064,815.70
    Construction Bid Price: $1,989,295.70
    Initial Construction Estimate: $2,959,647.00
    District: District 4

    Contracts (1) Progress
    # 56167 -- Construction Contract
    Arlington to Lincoln - Guide and Traffic Sign Replacement Along Route 2 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/09/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 12/27/2006
    Project Status Initiated 10/06/2006
    Project Status Advertised 06/14/2008
    Project Management
    100% Design 100% Package Received 04/10/2008
    100% Design 100% Package Comments to DE 05/01/2008
    100% Design 100% Plans Approved 04/30/2008
    25% Design 25% Package Received 03/19/2007
    25% Design 25% Package Comments to DE 03/27/2007
    25% Design 25% Package Approved 03/22/2007
    75% Design 75% Package Received 05/31/2007
    75% Design 75% Package Comments to DE 02/13/2008
    Final Design PS&E Received 05/29/2008
    Final Design PS&E to FAPRO 06/06/2008
    Consultant Contract Process NTP Issued 10/23/2006
    Consultant Contract Process Workhours Approved 10/19/2006