Project Description:
TEMPLETON- RECONSTRUCTION OF BALDWINVILLE ROAD, FROM ROUTE 202/68 TO PATRIOTS ROAD (APPROX. 3 MILES)
The project limits are from Route 202/68 to Route 101/2AA (Patriot Road) for a total length of 3.6 miles including approximately 2000 feet of State Highway Layout at Route 2. The improvements include a combination of coldplane and overlay, pavement reclamation and a short section of full-depth repair. New sidewalk with ADA compliant wheelchair ramps will be constructed on one side of the road for the entire length of the corridor. The roadway cross slope will be restored and drainage improvements will be constructed to eliminate ponding and icing conditions. Minor widening of the roadway is required to meet bicycle accommodation standards. Current widths vary between 26’ and 30’. A consistent 32’ width (12’ lanes, 4’ shoulders) is proposed. Sewer trenches that have settled will be repaired.
Location:
  • Town of Templeton
  • Resident Engineer: Ralph Romano
    Construction Contract Value: $4,310,977.00
    Construction Bid Price: $3,842,593.50
    Initial Construction Estimate: $4,404,550.50
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75234 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Baldwinville Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/04/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 11/28/2006
    Project Status Advertised 08/25/2012
    Project Management
    100% Design 100% Package Received 02/02/2012
    100% Design 100% Package Received 05/11/2012
    100% Design 100% Package Comments to DE 07/05/2012
    100% Design 100% Package Rejected 02/15/2012
    25% Design 25% Package Received 05/14/2009
    25% Design 25% Package Received 04/08/2011
    25% Design 25% Package Comments to DE 05/12/2010
    25% Design 25% Package Comments to DE 05/26/2011
    25% Design Design Public Hearing 07/13/2010
    75% Design 75% Package Received 09/16/2011
    Final Design PS&E Received 07/23/2012
    Final Design PS&E to FAPRO 08/22/2012