HARWICH- RECONSTRUCTION OF ROUTE 137, FROM QUEEN ANNE ROAD TO THE BREWSTER T.L.
Work on this project consists of reconstructing and box cut widening Route 137 from Queen Anne Road northerly to the Harwich/Brewster Town Line. The work also includes sidewalk installation, traffic signal installation at the Route 6 westbound off ramp, drainage improvements, pavement markings and sign installation.
Location:
  • Town of Harwich
  • Resident Engineer: Michael King
    Construction Contract Value: $3,520,499.00
    Construction Bid Price: $4,014,418.35
    Initial Construction Estimate: $4,752,797.00
    District: District 5

    Contracts (2) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70719 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route137 (Brewster and Chatham Roads). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/17/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 11/28/2006
    Project Status Advertised 08/27/2011
    Project Management
    100% Design 100% Package Received 05/25/2011
    100% Design 100% Package Comments to DE 08/01/2011
    25% Design 25% Package Received 05/12/2010
    25% Design 25% Package Comments to DE 11/17/2010
    25% Design 25% Package Approved 01/20/2011
    25% Design Design Public Hearing 01/19/2011
    Final Design PS&E Received 08/19/2011
    Final Design PS&E to FAPRO 08/22/2011