Project Description:
HARWICH- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 124 AND QUEEN ANNE ROAD
The project involves transportation improvements to the Queen Anne Road and Route 124 intersection located just south of the Route 6 (Mid-Cape Highway) Interchange #10. The poor level of service warrants the installation of a fully actuated traffic signal control system. Left turn lanes are proposed on both Route 124 approaches to improve overall operational characteristics. Other improvements include the following: expansion of the existing highway drainage system; revisions to travel lanes on the Route 124 southbound approach; truck turning movement improvements at the corners of the intersection; and pavement improvements with combined box widening and pavement overlays.
Location:
  • Town of Harwich
  • Resident Engineer: Joseph Gedraitis
    Construction Contract Value: $876,268.13
    Construction Bid Price: $759,842.05
    Initial Construction Estimate: $831,205.00
    District: District 5

    Contracts (1) Progress
    # 57007 -- Construction Contract
    Harwich - Roadway Reconstruction and Related work at Intersection of Route 124 (Plasant Lake Avenue) and Queen Anne Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/02/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 11/28/2006
    Project Status Advertised 08/02/2008
    Project Management
    100% Design 100% Package Received 06/23/2008
    100% Design 100% Package Comments to DE 07/15/2008
    25% Design 25% Package Received 03/19/2007
    25% Design 25% Package Comments to DE 09/07/2007
    25% Design Design Public Hearing 11/08/2007
    75% Design 75% Package Received 02/21/2008
    75% Design 75% Package Comments to DE 05/02/2008
    Final Design PS&E Received 07/25/2008
    Final Design PS&E to FAPRO 07/29/2008