NEW BEDFORD- BRIDGE PRESERVATION, N-06-014, I-195 OVER ROUTE 140
Location:
  • City of New Bedford
  • Resident Engineer: Francis Grenon
    Construction Contract Value: $10,770,390.75
    Construction Bid Price: $7,744,444.44
    Initial Construction Estimate: $8,716,817.00
    District: District 5

    Contracts (2) Progress
    # 54406 -- Construction Contract
    Bridge Replacement (N-06-014) (Steel) Route I-195 over Route 140 Completed
    # 55035 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/16/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 12/07/2006
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 07/03/2007
    25% Design 25% Package Received 03/09/2007
    Final Design PS&E to FAPRO 08/28/2007
    Consultant Contract Process NTP Issued 11/28/2006