Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LEOMINSTER- RECONSTRUCTION OF MECHANIC STREET, FROM LAUREL STREET TO THE LEOMINSTER CONNECTOR
Location:
  • City of Leominster
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Kimberley Sloan
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project