Project Description:
SOUTH HADLEY- BRIDGE PRESERVATION, S-18-015, ROUTE 202 OVER BARDWELL STREET & S-18-016, ROUTE 202 OVER ROUTE 116
The proposed work will consist of replacing the bridge decks on two adjacent bridges on US Route 202 over Bardwell St. and Route 116 (Newton St). The work also includes grading and paving of the approaches, replacement of guardrail and bridge rail, and minor repairs to the abutments. The work will be done in stages so that one lane of travel in each direction will be maintained during construction.
Location:
  • Town of South Hadley
  • Resident Engineer: Thomas Kozik
    Construction Contract Value: $4,076,923.86
    Construction Bid Price: $3,395,342.00
    Initial Construction Estimate: $4,604,152.25
    District: District 2

    Contracts (1) Progress
    # 57675 -- Construction Contract
    2 Bridge Rehabilitation (Steel) - (S-15-015) Route 202 over Bardwell Street and (S-18-016) Route 202 over Route 116. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/16/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 01/10/2007
    Project Status Advertised 10/11/2008
    Project Management
    100% Design 100% Package Received 11/14/2007
    100% Design 100% Package Comments to DE 01/08/2008
    75% Design 75% Package Received 11/14/2007
    Final Design PS&E Received 09/22/2008
    Final Design PS&E to FAPRO 09/23/2008
    Consultant Contract Process Scope to DE 02/26/2007
    Consultant Contract Process NTP Issued 03/28/2007