WOBURN- RECONSTRUCTION OF MONTVALE AVENUE, FROM I-93 INTERCHANGE TO CENTRAL STREET (APPROX. 1,850 FT)
This project will widen Montvale Avenue to 4 lanes and provide turning lanes at Washington Street. New traffic signals will be installed along with new sidewalks, wheelchair ramps and new roadway pavement
Location:
  • City of Woburn
  • Construction Begins: Spring 2018
    Resident Engineer: Michael Bartolo
    Construction Bid Price: $3,377,106.68
    District: District 4

    Contracts (1) Progress
    # 102207 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Montvale Avenue. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/22/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/22/2007
    Project Status Initiated 01/19/2007
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 02/10/2017
    100% Design 100% Package Comments to DE 03/23/2017
    25% Design 25% Package Received 07/09/2009
    25% Design 25% Package Received 06/18/2015
    25% Design 25% Package Comments to DE 10/28/2015
    25% Design Design Public Hearing 05/25/2016
    75% Design 75% Package Received 02/10/2017
    75% Design 75% Package Comments to DE 03/23/2017
    Final Design PS&E Received 08/02/2017
    Final Design PS&E to Peer Reviewer 03/09/2017
    Final Design Peer Review Comments to DE 04/17/2017
    Final Design PS&E to FAPRO 08/28/2017