Project Description: |
LEXINGTON- NEWTON- WALTHAM- WELLESLEY- WESTON- TRAFFIC SIGN REPLACEMENT ON I-95, FROM WELLESLEY (ROUTE 9) TO LEXINGTON (ROUTES 4/225) APPROX. 13 MILES
This project will replace and update all overhead and ground-mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the I-95 mainline and intersecting secondary roadways from the State Route 9 interchange in Wellesley northerly to the State Route 4/225 interchange in Lexington.
|
Location: |
|
Resident Engineer: | Martin McGowan |
Construction Contract Value: | $4,966,527.00 |
Construction Bid Price: | $4,429,570.09 |
Initial Construction Estimate: | $4,710,292.00 |
District: | District 4 |
|
Bridges |
|
|
|
|