SOMERVILLE- WILMINGTON- GUIDE & TRAFFIC SIGN REPLACEMENT ON I-93, FROM SULLIVAN SQUARE (EXIT 28) TO ROUTE 129 (EXIT 38)
This project will replace and update all overhead and ground-mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the I-93 mainline and intersecting secondary roadways from the Sullivan Square interchange in Somerville northerly to the State Route 129 interchange in Wilmington.
Location:
  • City of Somerville
  • Town of Wilmington
  • Resident Engineer: Mark Spinale
    Construction Contract Value: $5,070,466.52
    Construction Bid Price: $4,339,103.15
    Initial Construction Estimate: $5,252,277.00
    District: District 4

    Contracts (1) Progress
    # 63979 -- Construction Contract
    Guide and Traffic Sign Replacement along Interstate I-93. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/16/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee Letter 03/13/2007
    Project Status Initiated 01/23/2007
    Project Status Advertised 08/08/2009
    Project Status Advertised 04/24/2010
    Project Management
    100% Design 100% Package Received 03/06/2009
    25% Design 25% Package Received 02/08/2008
    25% Design 25% Package Comments to DE 03/11/2008
    25% Design 25% Package Approved 03/07/2008
    75% Design 75% Package Received 10/06/2008
    75% Design 75% Package Comments to DE 01/26/2009
    75% Design 75% Plans Approved 01/23/2009
    Final Design PS&E Received 04/15/2010
    Final Design PS&E to FAPRO 04/16/2010
    Consultant Contract Process Scope to DE 05/24/2007
    Consultant Contract Process NTP Issued 07/09/2007