Project Description:
BERKLEY- DIGHTON- BRIDGE REPLACEMENT (TEMP) B-08-001=D-08-011, ELM STREET OVER THE TAUNTON RIVER
The work to be done under this Contract involves the construction of a single lane bi-directional temporary bypass road and bridge adjacent to the existing Bridge No B-08-001 = D-08-011 carrying Elm Street in the Town of Berkley and Center Street in the Town of Dighton over the Taunton River. In addition the existing superstructure and a portion of the abutments of the existing Bridge No B-08-001 = D-08-011 will be demolished. The proposed work for the construction of temporary Bridge No B-08-001 = D-08-011 includes but is not limited to; construction of a new driven pipe pile founded substructure; erection of a new superstructure consisting of 700XS Acrow Panel bridge system units owned by the Massachusetts Highway Department and procurement of sufficient additional units to make a complete single lane bridge structure; design and construction of a modular retaining wall supporting each approach roadway embankment; construction of approach roadways and reconstruction of the existing roadways to tie in to the bypass road. The work also includes construction of traffic signals; demolition of the existing Bridge No B-08-001=D-08-011 superstructure and portions of the abutments and other items required to complete the work as shown on the drawings, as listed in the proposal, as specified herein, and as directed.
Location:
  • Town of Berkley
  • Town of Dighton
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $3,332,031.25
    Construction Bid Price: $2,459,245.00
    Initial Construction Estimate: $3,168,847.50
    District: District 5

    Contracts (1) Progress
    # 57633 -- Construction Contract
    Bridge Replacement (B-08-001=D-08-011 (Temp.) Elm Street / Center Street over the Taunton River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/13/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 01/24/2007
    Project Status Advertised 09/20/2008
    Project Management
    25% Design Design Public Hearing 09/18/2007
    Final Design PS&E Received 09/12/2008
    Final Design PS&E to FAPRO 09/16/2008
    Consultant Contract Process Scope to DE 12/05/2006
    Consultant Contract Process NTP Issued 01/04/2007