Project Description:
DISTRICT 5- MAINTENANCE OF STATE HIGHWAYS ON CAPE COD AND MARTHA'S VINEYARD (CONTRACT 5C)
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: Other
Project Manager: David Rock
Estimated Total Federal Participating Construction Cost: $2,271,295.50
District: District 5
Current Status: This project has been advertised for construction bids. (as of 04/07/2007 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/13/2007
    Project Status Initiated 01/24/2007
    Project Status Advertised 04/07/2007
    Project Management
    Final Design PS&E Received 03/26/2007
    Final Design PS&E to FAPRO 03/29/2007