Project Description: |
DISTRICT 5- DUMPING GROUND CLOSURES AT VARIOUS LOCATIONS IN DARTMOUTH, FREETOWN & WAREHAM
|
Location: | |
Resident Engineer: | Jeffrey Peterson |
Construction Contract Value: | $1,330,833.00 |
Construction Bid Price: | $1,017,793.00 |
Initial Construction Estimate: | $958,276.40 |
District: | District 5 |
|
Bridges |
|
|
|
|