UXBRIDGE- RECONSTRUCTION OF ROUTE 122 (NORTH MAIN STREET), FROM HARTFORD AVENUE TO ROUTE 16
The proposed improvements include a combination of reconstruction and resurfacing of the roadway, sidewalk construction or reconstruction and upgrade or installation of drainage structures.
Location:
  • Town of Uxbridge
  • Construction Begins: Spring 2020
    Resident Engineer: Scott Fitzgerald
    Construction Bid Price: $3,750,180.00
    District: District 3

    Contracts (2) Progress
    # 109684 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 122 (North Main Street) Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/21/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/08/2007
    Project Review Committee PRC Tabled 03/08/2007
    Project Review Committee PRC Approved 06/14/2007
    Project Review Committee Letter 09/06/2007
    Project Status Initiated 02/20/2007
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 12/15/2017
    100% Design 100% Package Comments to DE 01/23/2018
    25% Design 25% Package Received 02/04/2008
    25% Design 25% Package Comments to DE 03/24/2009
    25% Design Design Public Hearing 04/25/2013
    75% Design 75% Package Received 04/08/2015
    75% Design 75% Package Comments to DE 11/28/2016
    Final Design PS&E Received 08/10/2018
    Final Design PS&E to FAPRO 08/12/2019
    Final Design PS&E Received - Resub 1 03/06/2019
    Final Design PS&E Received - Resub 2 07/01/2019
    Final Design PS&E Received - Resub 3 07/10/2019