Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LYNN- SAUGUS- BRIDGE REPLACEMENT, L-18-016=S-05-008, ROUTE 107 OVER THE SAUGUS RIVER (AKA - BELDEN G. BLY BRIDGE)
This project consists of the construction of the Route 107 (Fox Hill bridge) which spans the Saugus River. The new bridge will serve as the permanent replacement for the proposed Temporary drawbridge. The new bridge (AKA Belden G. Bly bridge) will be a single leaf bascule drawbridge.
Location:
  • City of Lynn
  • Town of Saugus
  • Construction Begins: Autumn 2020
    Resident Engineer: Sean Magnus
    Construction Bid Price: $87,523,965.00
    District: District 4

    Contracts (10) Progress
    # 109691 -- Construction Contract
    Bridge Replacement (Belden G. Bly) Br. No. L-18-016=S-05-008 (Bascule) Route 107 (Salem Turnpike/Western Avenue) over the Saugus River 70% Complete
    # 115793 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 52072 -- Design -- Bridge Rehab/Recon/New Const
    Work includes design for replacing Bridge carrying State Route 107 over the Saugus River in Lynn and Saugus. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77882 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80640 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects
    # 80660 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 12/01/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/12/2007
    Project Status Initiated 02/21/2007
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 02/20/2018
    100% Design 100% Package Comments to DE 04/18/2018
    25% Design 25% Package Received 05/02/2016
    25% Design 25% Package Comments to DE 03/21/2012
    25% Design 25% Package Comments to DE 05/01/2012
    25% Design Design Public Hearing 11/02/2016
    75% Design 75% Package Received 07/20/2017
    Final Design PS&E Received 08/30/2019
    Final Design PS&E to FAPRO 08/30/2019