Project Description:
WORCESTER- RECONSTRUCTION & IMPROVEMENTS ON BELMONT STREET (WEST - ROUTE 9) FROM I-290 TO DANIELS STREET
The project is located on Belmont Street in Worcester from I-290 to Daniels Street, about 0.8 miles. The project includes minor widening and pavement overlay and related works.
Location:
  • City of Worcester
  • Resident Engineer: Neil Ahearn
    Construction Contract Value: $4,702,121.00
    Construction Bid Price: $4,169,746.95
    Initial Construction Estimate: $4,582,422.50
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70934 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Belmont Street (Route 9 W). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 02/26/2007
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 06/29/2011
    100% Design 100% Package Comments to DE 07/18/2011
    25% Design 25% Package Received 06/05/2009
    25% Design 25% Package Comments to DE 05/15/2009
    25% Design Design Public Hearing 11/16/2009
    75% Design 75% Package Received 05/11/2011
    75% Design 75% Package Comments to DE 06/17/2011
    Final Design PS&E Received 08/26/2011
    Final Design PS&E to FAPRO 08/31/2011