Project Description:
PEMBROKE- RECONSTRUCTION ON ROUTE 14, FROM THE HANSON T.L. TO WASHINGTON STREET (ROUTE 53)
The Route 14 reconstruction project consists of 3.3 miles of pavement rehabilitation and sidewalk reconstruction. The project starts at the Hanson town line and follows Maquan Street, Mattakeesett Street, Center Street, and Barker Street (to the intersection of Washington Street). The project consists of roadway widening in tandem with varying rehabilitation strategies along the corridor. Also included in the project are related items of work such as: sidewalk construction, drainage upgrades, culvert rehabilitation and new signing and striping.
Location:
  • Town of Pembroke
  • Construction Begins: Winter 2015/2016
    Resident Engineer: Russell Davis
    Construction Bid Price: $7,588,306.50
    District: District 5

    Contracts (1) Progress
    # 90573 -- Construction Contract
    Roadway Reconstruction and Related Work along Sections of Route 14 (Maquan, Mattakeesett, Center and Barker Streets). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/19/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 03/01/2007
    Project Status Advertised 09/12/2015
    Project Management
    100% Design 100% Package Received 04/05/2013
    100% Design 100% Package Comments to DE 01/07/2014
    25% Design 25% Package Received 08/28/2007
    25% Design 25% Package Received 03/08/2008
    25% Design 25% Package Comments to DE 11/15/2007
    25% Design Design Public Hearing 09/22/2009
    75% Design 75% Package Received 11/25/2009
    Final Design PS&E Received 08/10/2015
    Final Design PS&E Received 09/04/2015
    Final Design PS&E to FAPRO 09/08/2015