Project Description:
BRIDGEWATER- RECONSTRUCTION OF NORTH STREET, FROM PLEASANT STREET (ROUTE 104) TO VILLAGE GATE DRIVE
The purpose of this project is to reconstruct North Street from Pleasant Street to Village Gate Drive. The project will involve full depth reconstruction of North Street with approximately a four foot widening. A new sidewalk will be constructed on the east side of the roadway in order to provide pedestrian access to the new high school. Granite edging will be installed on the east side, and hot mix asphalt berm will be installed on the west side. A new closed drainage system will be provided to convey the storm water from North Street. The North Street /Pleasant Street intersection will be reconfigured to a more perpendicular approach.
Location:
  • Town of Bridgewater
  • Resident Engineer: John Bielski
    Construction Contract Value: $1,042,072.80
    Construction Bid Price: $791,378.10
    Initial Construction Estimate: $1,108,586.00
    District: District 5

    Contracts (1) Progress
    # 61790 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of North and Birch Streets and Village Gate Drive. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/21/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 03/08/2007
    Project Review Committee PRC Tabled 06/14/2007
    Project Review Committee Letter 10/18/2007
    Project Review Committee Resubmitted 09/13/2007
    Project Status Initiated 03/01/2007
    Project Status Advertised 12/05/2009
    Project Management
    100% Design 100% Package Received 09/04/2008
    100% Design 100% Package Comments to DE 11/12/2008
    100% Design 100% Plans Approved 09/25/2009
    25% Design 25% Package Received 06/15/2007
    25% Design 25% Package Comments to DE 11/05/2007
    25% Design Design Public Hearing 12/11/2007
    75% Design 75% Package Received 01/23/2008
    75% Design 75% Package Comments to DE 07/31/2008
    Final Design PS&E Received 09/25/2009
    Final Design PS&E to FAPRO 12/01/2009