Project Description: |
CLINTON- RECONSTRUCTION & RELATED WORK ON WATER STREET AND BOLTON ROAD (1.2 MILES)
Water Street will be reconstructed from High Street to the Clinton/Bolton town line, a project length of approximately 1.2 miles. The proposed improvements includes a combination of reconstruction and resurfacing, sidewalk construction or reconstruction, and upgrading or installation of drainage structures. The proposed widening will provide bicycle accommodation.
|
Location: |
|
Construction Begins: | Summer 2015 |
Resident Engineer: | Stephen Romano |
Construction Contract Value: | $4,433,939.40 |
Construction Bid Price: | $3,988,604.00 |
Initial Construction Estimate: | $4,285,000.00 |
District: | District 3 |
|
Bridges |
|
|
|
|