| Project Description: |
CLINTON- RESURFACING & RELATED WORK ON ROUTE 110 (HIGH STREET)
The projects extends on High Street (Route 110) from Water St to Allen St, approximately 0.6 miles. The proposed improvement include a combination of reconstruction and resurfacing, sidewalk construction or reconstruction, and improvements to drainage structures.
|
| Location: |
|
| Construction Begins: | Autumn 2019 |
| Resident Engineer: | Stephen Romano![]() |
| Construction Bid Price: | $2,170,629.75 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||