CLINTON- RESURFACING & RELATED WORK ON ROUTE 110 (HIGH STREET)
The projects extends on High Street (Route 110) from Water St to Allen St, approximately 0.6 miles. The proposed improvement include a combination of reconstruction and resurfacing, sidewalk construction or reconstruction, and improvements to drainage structures.
Location:
  • Town of Clinton
  • Construction Begins: Autumn 2019
    Resident Engineer: Stephen Romano
    Construction Bid Price: $2,170,629.75
    District: District 3

    Contracts (1) Progress
    # 108083 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 110 (High Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/11/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 03/21/2007
    Project Status Initiated 03/01/2007
    Project Status Advertised 06/15/2019
    Project Management
    100% Design 100% Package Received 09/07/2018
    100% Design 100% Package Comments to DE 11/13/2018
    25% Design 25% Package Received 09/04/2016
    25% Design 25% Package Comments to DE 08/29/2017
    25% Design Design Public Hearing 09/14/2017
    75% Design 75% Package Received 01/21/2018
    Final Design PS&E Received 02/04/2019
    Final Design PS&E to FAPRO 05/20/2019