Project Description:
HOLLAND- RESURFACING & RELATED WORK ON BRIMFIELD ROAD, FROM THE BRIMFIELD/HOLLAND T.L. TO WALES ROAD (1.4 MILES - PHASE I)
Project consists of reclamation and minor box-widening for improved bicycle accommodations. Additional work will include drainage improvements, new guardrail, new pavement markings, new signage , intersection improvements at Wales Road and other incidental work.
Location:
  • Town of Holland
  • Construction Begins: Summer 2019
    Resident Engineer: Richard Wonderlie
    Construction Bid Price: $2,178,954.60
    District: District 2

    Contracts (1) Progress
    # 107206 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Brimfield Road (Phase 1) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/18/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/08/2007
    Project Review Committee Letter 06/14/2007
    Project Status Initiated 03/02/2007
    Project Status Advertised 03/09/2019
    Project Management
    100% Design 100% Package Received 07/17/2018
    100% Design 100% Package Comments to DE 09/25/2018
    25% Design 25% Package Received 03/04/2013
    25% Design 25% Package Comments to DE 03/28/2014
    25% Design 25% Package Received - Resub 1 11/06/2017
    25% Design 25% Package Received - Resub 2 01/08/2018
    25% Design Design Public Hearing 02/15/2018
    75% Design 75% Package Received 03/19/2018
    75% Design 75% Package Comments to DE 04/23/2018
    Final Design PS&E Received 01/24/2019
    Final Design PS&E to FAPRO 02/25/2019
    Final Design PS&E Received - Resub 1 02/12/2019
    Final Design PS&E Received - Resub 2 02/20/2019