Project Description:
WESTFIELD- COLUMBIA GREENWAY RAIL TRAIL CONSTRUCTION (NORTH SECTION), FROM COWLES COURT ACCESS RAMPS TO THE WESTFIELD RIVER BRIDGE, INCLUDES REHAB OF W-25-036 (WESTFIELD RIVER CROSSING)
Phase III of this project involves construction of that portion of the trail from Cowles Court to the Westfield River, including work on the bridge crossing the Westfield River. The length of phase III is 853 ft or 0.16 mile.
Location:
  • City of Westfield
  • Construction Begins: Autumn 2016
    Resident Engineer: Adam Gauthier
    Construction Bid Price: $3,675,633.00
    District: District 2

    Contracts (1) Progress
    # 94995 -- Construction Contract
    Bridge Rehabilitation (Including Painting) along the Columbia Greenway Rail Trail Br. No. W-25-036 (Steel) over the Westfield River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/10/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 03/28/2007
    Project Status Advertised 06/25/2016
    Project Management
    100% Design 100% Package Received 08/06/2015
    100% Design 100% Package Comments to DE 12/09/2015
    25% Design 25% Package Received 05/23/2006
    25% Design 25% Package Comments to DE 05/31/2006
    25% Design Design Public Hearing 06/20/2006
    25% Design Design Public Hearing 11/13/2014
    75% Design 75% Package Received 10/01/2013
    75% Design 75% Package Comments to DE 12/04/2013
    Final Design PS&E Received 03/24/2016
    Final Design PS&E to FAPRO 06/21/2016