MERRIMAC- RECONSTRUCTION OF RIVER ROAD (EMERGENCY RELIEF)
The roadway was severely damaged by flooding in May 2006. The roadway has been closed since that time. The repairs include stabilizing the river bank, fixing the storm drain, repairing the guard rail and repairing/reconstructing the roadway surface. The reconstruction will be funded through the Federal Emergency Relief program.
Location:
  • Town of Merrimac
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Martin Leelman
    Estimated Total Federal Participating Construction Cost: $594,200.00
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 01/02/2010 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/14/2007
    Project Review Committee Letter 07/30/2007
    Project Status Initiated 04/19/2007
    Project Status Advertised 01/02/2010
    Project Management
    100% Design 100% Package Received 08/28/2009
    100% Design 100% Package Comments to DE 10/06/2009
    25% Design 25% Package Received 11/25/2008
    25% Design Design Public Hearing 04/21/2009
    75% Design 75% Package Received 11/25/2008
    75% Design 75% Package Comments to DE 03/30/2009
    Final Design PS&E Received 11/13/2009
    Final Design PS&E to FAPRO 11/25/2009