Project Description:
PEABODY- BRIDGE BETTERMENT, P-03-023 (RAMPS A&B) & P-03-024 (RAMPS G&F), I-95 RAMPS OVER STATE ROUTE 128
The proposed work for the I-95 Ramps over Route 128 in Peabody consists of replacing the bridge decks, adding cover plates to bridge P-03-024 and upgrading bridge and approach railings.
Location:
  • City of Peabody
  • Resident Engineer: Sean Magnus
    Construction Contract Value: $5,451,603.00
    Construction Bid Price: $4,565,429.00
    Initial Construction Estimate: $3,987,237.00
    District: District 4

    Contracts (3) Progress
    # 36570 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 56859 -- Construction Contract
    2 Bridge Rehabilitations Br. No. P-03-023 I-95 Ramps A & B over Route 128 and P-03-024 I-95 Ramp G over I-95 Ramp F (Painting Included) Completed
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/12/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/14/2007
    Project Review Committee PRC Tabled 06/14/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Status Initiated 05/01/2007
    Project Status Advertised 08/02/2008
    Project Management
    100% Design 100% Package Received 06/09/2008
    100% Design 100% Package Comments to DE 07/21/2008
    Final Design PS&E Received 06/19/2008
    Final Design PS&E to FAPRO 07/28/2008
    Consultant Contract Process Scope to DE 06/04/2007
    Consultant Contract Process NTP Issued 07/03/2007