Project Description:
DISTRICT 3- CRASH CUSHION REFURBISHMENT & IMPROVEMENTS
DISTRICT 3- CRASH CUSHION REFURBISHMENT & IMPROVEMENTS
Location:
Resident Engineer: Robert Babb Jr
Construction Contract Value: $127,391.50
Construction Bid Price: $99,911.00
Initial Construction Estimate: $108,681.00
District: District 3

Contracts (1) Progress
# 58728 -- Construction Contract
Crash Cushions System Refurbishment and Improvements at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/14/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/27/2007
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 06/18/2008
    Project Status Initiated 05/08/2007
    Project Status Advertised 05/02/2009
    Project Management
    Final Design PS&E Received 03/30/2009
    Final Design PS&E to FAPRO 04/28/2009