Project Description:
FRANKLIN- RECONSTRUCTION OF ROUTE 140, MAIN STREET & EMMONS STREET (DOWNTOWN ENHANCEMENTS) INCLUDES REHAB OF F-08-007 OVER MBTA
The project involves resurfacing and related work in Franklin Center on Route 140, Main and Emmons Streets. The work limits extend along Route 140 (West and East Central Streets), from Union Street to Alpine Place, along Main Street, from Route 140 to Pleasant Street, and along Emmons Street, from Route 140 to Ray Street with a total project length of approximately 7,150 linear feet (1.35 miles). The project includes mainly resurfacing, sidewalk reconstruction, lighting systems, installation of interconnected traffic signals, with emergency preemption system, traffic calming devices and streetscape/landscape improvements. The intent of the project is to preserve as much of the existing roadway and sidewalk structure as possible.
Location:
  • Town of Franklin
  • Resident Engineer: Anthony Tavalone
    Construction Contract Value: $6,254,802.50
    Construction Bid Price: $5,186,834.00
    Initial Construction Estimate: $5,120,852.87
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79872 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals and Street Lighting) on Sections of Eammons, Main, East and West Central Streets (Route140). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/21/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/14/2007
    Project Review Committee Letter 07/30/2007
    Project Status Initiated 05/18/2007
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 07/26/2013
    100% Design 100% Package Comments to DE 09/05/2013
    25% Design 25% Package Received 11/26/2010
    25% Design 25% Package Received 10/06/2011
    25% Design 25% Package Comments to DE 05/19/2011
    25% Design 25% Package Comments to DE 01/25/2012
    25% Design Design Public Hearing 06/28/2012
    75% Design 75% Package Received 09/17/2012
    75% Design 75% Package Received 03/13/2013
    75% Design 75% Package Comments to DE 12/05/2012
    75% Design 75% Package Comments to DE 05/24/2013
    Final Design PS&E Received 09/09/2013
    Final Design PS&E to FAPRO 09/10/2013