SOUTHBOROUGH- RECONSTRUCTION OF MAIN STREET (ROUTE 30), FROM SEARS ROAD TO PARK STREET
The purpose of this project is to reconstruct Main Street in Southborough with the intent to create a consistent roadway width. A continuous sidewalk will also be constructed along the southern side of the project. The intersection of Main Street (Route 30) and Marlborough Street/Cordaville Road (Route 85) are proposed to be realigned to include a new traffic signal system and left turn only lanes.
Location:
  • Town of Southborough
  • Construction Begins: Autumn 2018
    Resident Engineer: Anthony Tavalone
    Construction Bid Price: $6,732,884.00
    District: District 3

    Contracts (1) Progress
    # 103962 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of (Route 30) Main Street at (Route 85) Marlboro Street/Cordaville Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/16/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/14/2007
    Project Review Committee Letter 07/30/2007
    Project Status Initiated 05/18/2007
    Project Status Advertised 05/12/2018
    Project Management
    100% Design 100% Package Received 10/05/2017
    100% Design 100% Package Comments to DE 11/13/2017
    25% Design 25% Package Received 07/14/2008
    25% Design 25% Package Received 05/26/2011
    25% Design 25% Package Comments to DE 04/06/2009
    25% Design 25% Package Comments to DE 10/04/2011
    25% Design 25% Package Approved 01/18/2014
    25% Design Design Public Hearing 06/18/2014
    75% Design 75% Package Received 01/15/2016
    75% Design 75% Package Comments to DE 04/13/2016
    Final Design PS&E Received 03/06/2018
    Final Design PS&E to Peer Reviewer 03/28/2018
    Final Design Peer Review Comments to DE 04/19/2018
    Final Design PS&E to FAPRO 04/30/2018