Project Description:
WOBURN- BRIDGE REPLACEMENT, W-43-017, NEW BOSTON STREET OVER MBTA
The work proposed in this project consists of constructing a new bridge over the NH Main Line of the MBTA Commuter Rail. Also included is the reconstruction of approximately 1,850 feet of New Boston Street.
Location:
  • City of Woburn
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2021/2022
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $22,355,161.15
    Estimated Total Federal Participating Construction Cost: $24,795,282.90
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 09/11/2021 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WOBURN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG revised from $18,280,891 to $23,514,385 via STIP Action 6.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $18,811,508.00
    State Cost: $4,702,877.00
    Total Cost: $23,514,385.00

    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/14/2007
    Project Review Committee Letter 07/30/2007
    Project Status Initiated 05/29/2007
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 08/03/2020
    100% Design 100% Package Comments to DE 10/23/2020
    25% Design 25% Package Received 04/22/2016
    75% Design 75% Package Received 06/20/2019
    75% Design 75% Package Comments to DE 03/09/2020
    Final Design PS&E Received 05/10/2021
    Final Design PS&E to FAPRO 08/27/2021