MALDEN- REVERE- SAUGUS- RECONSTRUCTION & WIDENING ON ROUTE 1, FROM ROUTE 60 TO ROUTE 99
The purpose of this project is to eliminate a bottleneck on Route 1 in the project area by adding a lane in each direction for a consistent six-lane facility in order to improve traffic flow and safety. The project would provide improvements to the 2.4 mile section of Route 1 from 1,500 feet south of the Route 1/Route 60 Interchange (Copeland Circle) north through the Route 1/Route 99 interchange. The project includes reconfiguration of the Route 1/Salem Street and Route 1/Lynn Street interchanges, and the construction of a new ramp from Route 1 South to Route 60 South (Squire Road) at Copeland Circle. The major benefits of the project are: the establishment of a consistent cross section for Route 1 to eliminate a bottleneck; and the elimination of substandard exit and entrance ramps.
Location:
  • City of Malden
  • City of Revere
  • Town of Saugus
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: John Fallon
    Estimated Total Contract Cost: $165,000,000.00
    Estimated Total Federal Participating Construction Cost: $172,500,000.00
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/28/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 10/10/2007
    Project Status Initiated 06/08/2007
    Project Management