Project Description:
WOBURN- NOISE BARRIER CONSTRUCTION ON I-93
The project involves the construction of a Type II Noise Barrier along I-93 Southbound in Woburn. The barrier will be approximately 3800 feet long and approximately 16 feet high. The barrier will start south of the I-95 interchange and extend southerly to the Montvale Avenue interchange.
Location:
  • City of Woburn
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: James Cerbone
    Estimated Total Contract Cost: $4,590,724.60
    Estimated Total Federal Participating Construction Cost: $5,008,063.20
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/27/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 11/20/2007
    Project Status Initiated 06/08/2007
    Project Management