BURLINGTON- LEXINGTON- READING- WOBURN- TRAFFIC SIGN & GUIDE REPLACEMENT ON I-95 (SR 128)
This project will replace and upgrade all guide, regulatory, and warning signing on I-95 between US 3 (Exit 32) in Lexington and I-93 (Exit 37) in Reading, including applicable signing on intersecting roadways.
Location:
  • Town of Burlington
  • Town of Lexington
  • Town of Reading
  • City of Woburn
  • Resident Engineer: Michael McGeoch
    Construction Contract Value: $2,926,231.52
    Construction Bid Price: $2,571,730.47
    Initial Construction Estimate: $3,076,870.00
    District: District 4

    Contracts (1) Progress
    # 58184 -- Construction Contract
    Guide and Traffic Sign Replacement on a Section of Interstate I-95 (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/23/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/26/2007
    Project Initiation Form PIF Entered 06/26/2007
    Project Initiation Form PRC Submitted 07/02/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Status Advertised 03/14/2009
    Project Management
    100% Design 100% Package Comments to DE 02/12/2009
    100% Design 100% Plans Approved 02/12/2009
    25% Design 25% Package Comments to DE 05/29/2008
    25% Design 25% Package Approved 05/27/2008
    75% Design 75% Package Received 08/27/2008
    75% Design 75% Package Comments to DE 10/29/2008
    75% Design 75% Plans Approved 10/27/2008
    75% Design 75% Plans Complete 10/27/2008
    Final Design PS&E Received 02/27/2009
    Final Design PS&E to FAPRO 03/03/2009
    Consultant Contract Process Scope to DE 10/01/2007
    Consultant Contract Process NTP Issued 10/25/2007
    Consultant Contract Process Workhours Approved 10/25/2007