Project Description:
SALISBURY- MULTI-USE TRAIL EXTENSION (BORDERS TO BOSTON TRAIL), INCLUDES NEW BRIDGE S-02-004 AND BOARDWALK (S-02-012 (BYX)
The Salisbury section of the Border to Boston Trail is approximately 2.287 miles, which will extend from Mudnock Road to the New Hampshire border.
Location:
  • Town of Salisbury
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Kenneth Wong
    Construction Bid Price: $5,644,722.00
    District: District 4

    Contracts (4) Progress
    # 105648 -- Construction Contract
    Construction of a Shared Use Path (Border to Boston Trail Extension) from Mudnock Road to Collins Street Including Bridge No. S-02-004 and Boardwalk Br. No. S-02-012 Completed
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66262 -- Design -- Bike/Ped Projects
    Work will consist of the preparation of the final PS&E for a section of the Border to Boston Trail Project extending from Boxford to Salisbury Final
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/18/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2007
    Project Initiation Form PIF Entered 07/31/2007
    Project Initiation Form PRC Submitted 08/17/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 11/20/2007
    Project Status Advertised 08/25/2018
    Project Management
    100% Design 100% Package Received 04/27/2018
    100% Design 100% Package Comments to DE 06/01/2018
    25% Design 25% Package Received 09/04/2012
    25% Design 25% Package Comments to DE 11/21/2012
    25% Design Design Public Hearing 06/08/2015
    75% Design 75% Package Received 12/18/2017
    75% Design 75% Package Comments to DE 02/22/2018
    Final Design PS&E Received 07/12/2018
    Final Design PS&E Received - Resub 2 08/06/2018