Project Description:
WILMINGTON- INTERSECTION IMPROVEMENTS ON ROUTE 62 (MIDDLESEX AVENUE) @ GLENN ROAD AND WILDWOOD STREET
The project involves the installation of new traffic signal at the intersection of Route 62 (Middlesex Avenue) at Glen Road and Wildwood Street, reconfiguration of Glen Road intersection and widening of Route 62 (Middlesex Avenue) and Glen Road.
Location:
  • Town of Wilmington
  • Resident Engineer: Michael Bartolo
    Construction Contract Value: $1,192,541.44
    Construction Bid Price: $1,276,969.67
    Initial Construction Estimate: $1,301,887.50
    District: District 4

    Contracts (1) Progress
    # 84975 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) along a Section of Route 62 (Middlesex Avenue) at Glen Road and Wildwood Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2007
    Project Initiation Form PIF Entered 06/28/2007
    Project Initiation Form PRC Submitted 07/02/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 10/27/2010
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 11/08/2013
    100% Design 100% Package Comments to DE 01/08/2014
    100% Design 100% Plans Approved 01/24/2014
    100% Design 100% Plans Complete 01/14/2014
    25% Design 25% Package Received 08/13/2009
    25% Design 25% Package Comments to DE 05/26/2011
    25% Design Design Public Hearing 09/24/2012
    75% Design 75% Package Received 07/23/2013
    75% Design 75% Package Comments to DE 10/17/2013
    Final Design PS&E Received 02/11/2014
    Final Design PS&E to FAPRO 09/10/2014