MERRIMAC- EMERGENCY RELIEF PROGRAM, M-16-001 (CULVERT), RIVER ROAD OVER COBBLER'S BROOK
The project involves work on the Cobbler's Brook Bridge including repairs to the masonry arch, spandrel wall, wing wall, repairs to the metal plate arch footings with the use of a grouted liner, repair of the plate arch/masonry arch transition, installation of guardrail and resurfacing the roadway.
Location:
  • Town of Merrimac
  • Resident Engineer: Jeffrey Lavallee
    Construction Contract Value: $531,995.00
    Construction Bid Price: $478,359.51
    Initial Construction Estimate: $508,355.00
    District: District 4

    Contracts (2) Progress
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 63977 -- Construction Contract
    Bridge Rehabilitation (M-16-001) (Concrete) – River Road over Cobbler’s Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/27/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: EMERGENCY RELIEF
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/29/2007
    Project Initiation Form PIF Entered 06/29/2007
    Project Initiation Form PRC Submitted 07/06/2007
    Project Review Committee PRC Approved 09/13/2007
    Project Review Committee Letter 04/29/2009
    Project Status Advertised 04/17/2010
    Project Management
    100% Design 100% Package Received 12/22/2009
    25% Design 25% Package Received 09/18/2009
    25% Design 25% Package Comments to DE 05/20/2009
    25% Design 25% Package Comments to DE 07/23/2009
    75% Design 75% Package Received 09/18/2009
    75% Design 75% Package Comments to DE 11/06/2009
    Final Design PS&E Received 04/12/2010
    Final Design PS&E to FAPRO 04/13/2010