Project Description: |
NEW ASHFORD- LANESBOROUGH- RESURFACING & RELATED WORK ON ROUTE 7, FROM MM 41.68 TO MM 45.05
This project proposes to resurface Route 7 with hot-mix asphalt, and would also include repairing/improving the drainage system, resetting guardrail, upgrading guardrail end treatments, re-establishing and stabilizing roadway shoulders with dense graded crushed stone, applying thermoplastic pavement markings and providing new traffic signs as required.
|
Location: |
|
Resident Engineer: | Glenn Cellana |
Construction Contract Value: | $2,223,781.00 |
Construction Bid Price: | $1,965,710.00 |
Initial Construction Estimate: | $1,691,289.00 |
District: | District 1 |
|
Bridges |
|
|
|
|