Project Description:
HADLEY- RECONSTRUCTION ON ROUTE 9, FROM MIDDLE STREET TO MAPLE/SOUTH MAPLE STREET
The proposed roadway design widens Russell Street through full depth reconstruction to provide two travel lanes in each direction with a minimum lane width of 11 feet and a shoulder width of 4 feet. The proposed pavement width will vary from 52 to 82 feet wide curb-to-curb. The proposed shoulder width of 4 feet will be an improvement over the existing shoulders which are as narrow as 2 foot wide. The widening of the roadway from one travel lane in each direction to two travel lanes in each direction will add additional capacity and improved traffic progression. Other improvements to Russell Street include the following: increasing roadway vertical grades to improve surface drainage; upgrading the existing storm system drainage; new traffic signage; extending or replacing existing cross culverts; installing raised pavement markers; new granite curbs; new 6.5-foot wide concrete sidewalks along both sides of the roadway. The project starts at Station 157+49.38 (Lowe's Driveway)and ends at Station 189+10.94 (Home Depot/Mountain Farms Mall Driveway).
Location:
  • Town of Hadley
  • Construction Begins: Winter 2021/2022
    Resident Engineer: John Dahl
    Construction Bid Price: $25,664,749.00
    District: District 2

    Contracts (4) Progress
    # 116287 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Russell Street (Route 9) 70% Complete
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/12/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/15/2007
    Project Initiation Form PIF Entered 08/31/2007
    Project Initiation Form PRC Submitted 09/06/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 10/10/2007
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 06/15/2020
    100% Design 100% Package Comments to DE 08/20/2020
    25% Design 25% Package Received 10/12/2017
    25% Design 25% Package Received - Resub 1 10/05/2018
    25% Design Design Public Hearing 06/25/2019
    75% Design 75% Package Received 11/19/2019
    75% Design 75% Package Comments to DE 01/21/2020
    Final Design PS&E Received 04/20/2021
    Final Design PS&E Received - Resub 1 08/09/2021