Project Description:
PLYMOUTH- RECONSTRUCTION OF TAYLOR AVENUE, FROM WHITE HORSE ROAD TO MANOMET POINT ROAD, INCLUDES BRIDGE REPLACEMENT OF P-13-010
Work on this project will consist of roadway reconstruction, sidewalk installation and reconstruction, installation of a closed drainage system and replacement of the bridge carrying Taylor Avenue over Bridge Dam Brook. The work will improve roadway functionality, pedestrian/bicycle mobility and existing drainage issues in the Taylor Avenue corridor.
Location:
  • Town of Plymouth
  • Construction Begins: Summer 2018
    Resident Engineer: Daniel Mastrangelo
    Construction Bid Price: $6,459,118.90
    District: District 5

    Contracts (1) Progress
    # 102199 -- Construction Contract
    Roadway Reconstruction and Related Work including Replacement of Br. No. P-13-010 (Pre-Stressed Concrete Deck Beams) Taylor Avenue over Beaver Dam Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/29/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2007
    Project Initiation Form PIF Entered 09/05/2007
    Project Initiation Form PRC Submitted 09/10/2007
    Project Review Committee PRC Approved 09/10/2007
    Project Review Committee Letter 11/15/2007
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 01/10/2017
    25% Design 25% Package Received 11/05/2007
    25% Design 25% Package Comments to DE 09/01/2009
    25% Design 25% Package Comments to DE 01/07/2010
    25% Design Design Public Hearing 04/09/2009
    75% Design 75% Package Received 03/03/2011
    75% Design 75% Package Comments to DE 06/14/2014
    Final Design PS&E Received 05/31/2017
    Final Design PS&E to Peer Reviewer 08/10/2016
    Final Design PS&E to Peer Reviewer 02/15/2017
    Final Design Peer Review Comments to DE 08/29/2016
    Final Design Peer Review Comments to DE 03/24/2017
    Final Design PS&E Received - Resub 2 08/11/2017