Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
PLYMOUTH- RECONSTRUCTION OF TAYLOR AVENUE, FROM WHITE HORSE ROAD TO MANOMET POINT ROAD, INCLUDES BRIDGE REPLACEMENT OF P-13-010
Work on this project will consist of roadway reconstruction, sidewalk installation and reconstruction, installation of a closed drainage system and replacement of the bridge carrying Taylor Avenue over Bridge Dam Brook. The work will improve roadway functionality, pedestrian/bicycle mobility and existing drainage issues in the Taylor Avenue corridor.
Location:
  • Town of Plymouth
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Thomas H Currier
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • P13010 
    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project