BECKET- BRIDGE PRESERVATION, B-03-016, McNERNEY ROAD OVER SHAKER MILL BROOK
The proposed work for the bridge carrying McNerney Road over Shaker Mill Brook will consist of replacing the existing metal arch with a rigid concrete frame that will be designed for AASHTO HS25 Loading. The work will involve stream bed restoration to address the local scour issues.
Location:
  • Town of Becket
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Hemendra Bhatt
    Estimated Total Contract Cost: $1,032,378.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • B03016 
    See the Milestone Details tab for additional Project information