BECKET- BRIDGE PRESERVATION, B-03-016, McNERNEY ROAD OVER SHAKER MILL BROOK
The proposed work for the bridge carrying McNerney Road over Shaker Mill Brook will consist of replacing the existing metal arch with a rigid concrete frame that will be designed for AASHTO HS25 Loading. The work will involve stream bed restoration to address the local scour issues.
Location:
  • Town of Becket
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $1,032,378.00
    Construction Bid Price: $859,482.00
    Initial Construction Estimate: $1,118,343.00
    District: District 1

    Contracts (2) Progress
    # 44056 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 57889 -- Construction Contract
    Bridge Replacement (B-03-016) (Concrete) - McNerney Road and Shaker Mill Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/16/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/11/2007
    Project Initiation Form PIF Entered 12/03/2007
    Project Initiation Form PRC Submitted 12/03/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 02/07/2008
    Project Status Advertised 12/13/2008
    Project Management
    100% Design 100% Package Received 05/15/2008
    100% Design 100% Package Comments to DE 07/24/2008
    Final Design PS&E Received 08/22/2008
    Final Design PS&E to FAPRO 12/08/2008
    Consultant Contract Process Scope to DE 09/21/2007
    Consultant Contract Process NTP Issued 11/09/2007