Project Description:
DISTRICT 5- SIDEWALK CONSTRUCTION & RECONSTRUCTION AT VARIOUS LOCATIONS
Reconstruction of existing sidewalk and construction of proposed sidewalk at various locations in District 5.
Location:
Resident Engineer: Stephen Soares
Construction Contract Value: $1,010,198.02
Construction Bid Price: $889,337.50
Initial Construction Estimate: $1,102,889.00
District: District 5

Contracts (2) Progress
# 51303 -- Design -- Hwy Eng Open End
Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
# 58838 -- Construction Contract
Sidewalk Construction and Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/28/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/13/2007
    Project Initiation Form PIF Entered 05/28/2008
    Project Initiation Form PRC Submitted 05/28/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 06/18/2008
    Project Status Advertised 04/25/2009
    Project Management
    Final Design PS&E Received 07/24/2008
    Final Design PS&E to FAPRO 11/17/2008