Project Description:
MEDFORD- SOMERVILLE- INTERSTATE MAINTENANCE & RELATED WORK ON I-93
The work for this project includes resurfacing, cold-planing and placement of hot mix asphalt, adjustment of drainage and utility structures, guardrail repairs and/or upgrades, maintenance related work on bridge decks and joints, and placment of pavement markings. The project starts in Somerville at MM 20.85, thence northerly through the Medford/Somerville City Line to the Medford/Stoneham Town Line ending approximately at MM 24.55. Work shall also include all ramp systems and interchanges within the above I-93 mainline limits. Project length is 4.0 miles (approximately 21,120 linear feet.).
Location:
  • City of Medford
  • City of Somerville
  • Resident Engineer: Robert Blackmar
    Construction Contract Value: $13,792,781.00
    Construction Bid Price: $12,171,664.68
    Initial Construction Estimate: $9,061,964.00
    District: District 4

    Contracts (1) Progress
    # 55420 -- Construction Contract
    Work consists of resurfacing and related work on Route I-93 both Northbound and Southbound in the Cities of Medford and Somerville. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/28/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/24/2007
    Project Initiation Form PIF Entered 09/24/2007
    Project Initiation Form PRC Submitted 10/02/2007
    Project Review Committee Letter 12/14/2007
    Project Status Advertised 04/26/2008
    Project Status Advertised 05/17/2008
    Project Management
    75% Design 75% Package Received 12/04/2007
    Final Design PS&E Received 03/13/2008
    Final Design PS&E to FAPRO 03/14/2008