Project Description:
PEABODY- DANVERS- TOPSFIELD- BOXFORD- GEORGETOWN- TRAFFIC SIGN REPLACEMENT & RELATED WORK ON I-95
This project will replace and update all overhead and ground-mounted directional and traffic signs along I-95, including applicable signing on intersecting secondary roadways, from Exit 46 (US 1 South) in Peabody northerly to Exit 54 (State Route 133) in Georgetown.
Location:
  • Town of Boxford
  • Town of Danvers
  • Town of Georgetown
  • City of Peabody
  • Town of Topsfield
  • Resident Engineer: Philip Jodoin
    Construction Contract Value: $3,276,489.00
    Construction Bid Price: $2,876,990.70
    Initial Construction Estimate: $3,580,725.00
    District: District 4

    Contracts (1) Progress
    # 75715 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide Sgns along a Section of Interstate 95. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/10/2007
    Project Initiation Form PIF Entered 10/24/2007
    Project Initiation Form PRC Submitted 10/24/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 12/17/2007
    Project Status Advertised 09/22/2012
    Project Management
    100% Design 100% Package Received 01/14/2010
    100% Design 100% Package Comments to DE 01/27/2010
    100% Design 100% Plans Approved 01/26/2010
    25% Design 25% Package Received 10/30/2008
    25% Design 25% Package Comments to DE 01/29/2009
    25% Design 25% Package Approved 01/28/2009
    75% Design 75% Package Received 05/21/2009
    75% Design 75% Plans Complete 07/24/2009
    Final Design PS&E Received 02/03/2010
    Final Design PS&E to FAPRO 09/11/2012
    Consultant Contract Process Scope to DE 01/15/2008
    Consultant Contract Process NTP Issued 02/19/2008