Project Description:
WORCESTER- RECONSTRUCTION OF LINCOLN STREET (ROUTE 70), FROM MARSH AVENUE TO PLANTATION STREET (PHASE II)
The project’s proposed Phase 2 Lincoln Street Reconstruction stretches from Marsh Avenue to Plantation Street. The work includes widening of Lincoln Street to include a 4-foot wide shoulder on each side, new sidewalks, and turning lanes at Lincoln Plaza; reconfiguring the Lincoln Street and Pasadena Parkway intersection; and a roundabout at the intersection of Lincoln Street, Boylston Street and Benson Avenue. The traffic signals will be updated and coordinated along Lincoln Street, at its intersections with: 1) Goldthwaite Road and Trinity Avenue, 2) Country Club Boulevard, 3) Lincoln Plaza West and East Driveways; and 4) at the pedestrian crossing near Tyler Prentice Road. Bicycle accommodations consisting of 4-foot wide shoulders have been provided in accordance with applicable design guides.
Location:
  • City of Worcester
  • Resident Engineer: Steven Miller
    Construction Contract Value: $7,290,302.95
    Construction Bid Price: $6,261,584.50
    Initial Construction Estimate: $5,590,428.00
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84665 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Lincoln Street (Route 70) (Phase II). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/02/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/11/2007
    Project Initiation Form PIF Entered 12/07/2007
    Project Initiation Form PRC Submitted 12/07/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 02/19/2008
    Project Status Advertised 09/06/2014
    Project Management
    100% Design 100% Package Received 06/16/2014
    100% Design 100% Package Comments to DE 08/11/2014
    25% Design 25% Package Received 01/20/2011
    25% Design 25% Package Comments to DE 05/01/2013
    25% Design Design Public Hearing 06/11/2013
    75% Design 75% Package Received 12/04/2013
    75% Design 75% Package Comments to DE 02/21/2014
    Final Design PS&E Received 08/29/2014
    Final Design PS&E to Peer Reviewer 08/12/2014
    Final Design Peer Review Comments to DE 08/25/2014
    Final Design PS&E to FAPRO 09/02/2014