CHICOPEE-WEST SPRINGFIELD- BRIDGE PRESERVATION, C-13-034=W-21-043, I-91 OVER CONNECTICUT RIVER
The proposed work for the bridge carrying I-91 over the Connecticut River consists of retrofitting the Pin and Hanger assemblies on these structures. This work will be performed to avoid load posting Interstate I-91 for the numerical load rating values, provide a system redundancy, and reduce the potential for failure associated with the existing fracture critical detailing.
|
| Location: |
|
| Resident Engineer: | George Pelletier![]() |
| Construction Contract Value: | $3,928,722.50 |
| Construction Bid Price: | $3,329,637.50 |
| Initial Construction Estimate: | $1,572,913.00 |
| District: | District 2 |
|