Project Description: |
CHICOPEE-WEST SPRINGFIELD- BRIDGE PRESERVATION, C-13-034=W-21-043, I-91 OVER CONNECTICUT RIVER
The proposed work for the bridge carrying I-91 over the Connecticut River consists of retrofitting the Pin and Hanger assemblies on these structures. This work will be performed to avoid load posting Interstate I-91 for the numerical load rating values, provide a system redundancy, and reduce the potential for failure associated with the existing fracture critical detailing.
|
Location: |
|
Resident Engineer: | George Pelletier |
Construction Contract Value: | $3,928,722.50 |
Construction Bid Price: | $3,329,637.50 |
Initial Construction Estimate: | $1,572,913.00 |
District: | District 2 |
|
Bridges
|
|
|
|
|