PITTSFIELD- SIGNAL & INTERSECTION IMPROVEMENTS @ WEST STREET (STATE ROUTE 9) & CENTER STREET
This project will upgrade an existing traffic signal, and associated components, from a cam/ratchet driven mechanical system with pre-timed cycles to a fully actuated signal that can be optimized for traffic flow. This intersection was one of several recommended for improvement in the Berkshire MPO's Downtown Circulation Study for Pittsfield.
Location:
  • City of Pittsfield
  • Resident Engineer: Stephen Eddington
    Construction Contract Value: $695,743.00
    Construction Bid Price: $597,338.00
    Initial Construction Estimate: $696,287.00
    District: District 1

    Contracts (1) Progress
    # 57453 -- Construction Contract
    Intersection Reconstruction and Related Work at Route 9 (West Street) and Center Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/26/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/31/2007
    Project Initiation Form PIF Entered 10/31/2007
    Project Initiation Form PRC Submitted 11/26/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 02/07/2008
    Project Status Advertised 09/20/2008
    Project Management
    100% Design 100% Package Received 08/01/2008
    25% Design 25% Package Received 02/22/2008
    25% Design 25% Package Comments to DE 05/27/2008
    25% Design Design Public Hearing 07/09/2008
    75% Design 75% Package Received 08/01/2008
    Final Design PS&E Received 09/16/2008