Project Description: |
PITTSFIELD- SIGNAL & INTERSECTION IMPROVEMENTS @ WEST STREET (STATE ROUTE 9) & CENTER STREET
This project will upgrade an existing traffic signal, and associated components, from a cam/ratchet driven mechanical system with pre-timed cycles to a fully actuated signal that can be optimized for traffic flow. This intersection was one of several recommended for improvement in the Berkshire MPO's Downtown Circulation Study for Pittsfield.
|
Location: |
|
Resident Engineer: | Stephen Eddington |
Construction Contract Value: | $695,743.00 |
Construction Bid Price: | $597,338.00 |
Initial Construction Estimate: | $696,287.00 |
District: | District 1 |
|
Bridges |
|
|
|
|