Project Description:
NORTHAMPTON- INTERSECTION IMPROVEMENTS AT ROUTE 5 (PLEASANT STREET) AND CONZ STREET
The intersection of Pleasant Street and Conz Street is a documented high crash location, appearing in the list of 2009 HSIP Clusters in Pioneer Valley. Driveways intersect with Route 5 at this intersection, creating confusion and conflicts. High volumes result in delays. The current preferred alternative would convert the unsignalized intersection to a single-lane roundabout, resurface intersection approaches, and provide new pavement markings, sidewalks, wheelchair ramps and crosswalks, and bus pullouts.
Location:
  • City of Northampton
  • Resident Engineer: Garrett Postema
    Construction Bid Price: $2,207,838.65
    District: District 2

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72503 -- Design -- Traffic Signing/Signals
    Work will consist of providing engineering services in connection with the design and modifications to the statewide highway lighting systems. Final
    # 88202 -- Construction Contract
    Roundabout Construction and Related Work at Conz and Pleasant Streets (Route 5). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/04/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/28/2007
    Project Initiation Form PIF Entered 09/30/2010
    Project Initiation Form PRC Submitted 09/30/2010
    Project Review Committee PRC Approved 12/13/2007
    Project Status Advertised 05/23/2015
    Project Management
    100% Design 100% Package Received 11/25/2014
    100% Design 100% Package Comments to DE 12/26/2014
    25% Design 25% Package Received 07/23/2012
    25% Design 25% Package Comments to DE 11/16/2012
    25% Design Design Public Hearing 04/24/2013
    75% Design 75% Package Received 02/12/2014
    75% Design 75% Package Comments to DE 04/08/2014
    Final Design PS&E Received 04/07/2015
    Final Design PS&E Received 09/09/2015
    Final Design PS&E to FAPRO 05/20/2015
    Final Design PS&E to FAPRO 09/09/2015
    Consultant Contract Process Scope to DE 12/20/2010
    Consultant Contract Process NTP Issued 05/09/2011
    Consultant Contract Process Workhours Approved 04/11/2011