FALL RIVER- RECONSTRUCTION & TRAFFIC SIGNAL IMPROVEMENTS ON PLYMOUTH AVENUE, FROM WORDELL STREET TO RHODE ISLAND AVENUE AT SLADE STREET/LAUREL STREET
Work on this project will consist of roadway rehabilitation and resurfacing, traffic signal improvements, sidewalk reconstruction, drainage upgrades, new curbing and some resetting of existing curbing, pavement markings including striping of bicycle lanes and sign installation.
Location:
  • City of Fall River
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $8,524,907.03
    Construction Bid Price: $7,329,892.80
    Initial Construction Estimate: $7,585,791.00
    District: District 5

    Contracts (2) Progress
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 73930 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Plymouth Avenue (Route 81). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/19/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/03/2007
    Project Initiation Form PIF Entered 12/03/2007
    Project Initiation Form PRC Submitted 12/04/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Status Advertised 05/26/2012
    Project Management
    100% Design 100% Package Received 03/01/2012
    100% Design 100% Package Comments to DE 04/04/2012
    25% Design 25% Package Received 02/08/2010
    25% Design 25% Package Comments to DE 12/01/2010
    25% Design Design Public Hearing 03/30/2011
    75% Design 75% Package Received 06/07/2011
    75% Design 75% Package Comments to DE 11/15/2011
    Final Design PS&E Received 05/11/2012
    Final Design PS&E to FAPRO 05/24/2012