Project Description: |
FALL RIVER- RECONSTRUCTION & TRAFFIC SIGNAL IMPROVEMENTS ON PLYMOUTH AVENUE, FROM WORDELL STREET TO RHODE ISLAND AVENUE AT SLADE STREET/LAUREL STREET
Work on this project will consist of roadway rehabilitation and resurfacing, traffic signal improvements, sidewalk reconstruction, drainage upgrades, new curbing and some resetting of existing curbing, pavement markings including striping of bicycle lanes and sign installation.
|
Location: |
|
Resident Engineer: | Rajat Gogoi |
Construction Contract Value: | $8,524,907.03 |
Construction Bid Price: | $7,329,892.80 |
Initial Construction Estimate: | $7,585,791.00 |
District: | District 5 |
|