NEW BEDFORD- RECONSTRUCTION OF MILL STREET, FROM PLEASANT STREET TO KEMPTON STREET
Work on this project in New Bedford consists of the reconstruction of Mill Street including: traffic signal installation; intersection improvements; sidewalk upgrades; curb installation and resetting of existing curb; drainage upgrades; pavement markings and sign installation.
Location:
  • City of New Bedford
  • Resident Engineer: Emanuel Aguiar
    Construction Contract Value: $3,993,327.00
    Construction Bid Price: $3,444,908.85
    Initial Construction Estimate: $3,873,382.50
    District: District 5

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 69938 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Mill Street (Route 6 WB). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/15/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/04/2007
    Project Initiation Form PIF Entered 12/04/2007
    Project Initiation Form PRC Submitted 12/04/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 02/19/2008
    Project Status Advertised 07/16/2011
    Project Management
    100% Design 100% Package Received 02/04/2011
    100% Design 100% Package Comments to DE 05/20/2011
    100% Design 100% Plans Approved 05/13/2011
    25% Design 25% Package Received 03/31/2009
    25% Design 25% Package Comments to DE 12/21/2009
    25% Design 25% Package Approved 12/21/2009
    25% Design Design Public Hearing 04/06/2010
    75% Design 75% Package Received 06/07/2010
    75% Design 75% Package Comments to DE 12/03/2010
    75% Design 75% Plans Approved 12/03/2010
    Final Design PS&E Received 06/20/2011
    Final Design PS&E to FAPRO 07/13/2011