Project Description:
NORTH ADAMS- DOWNTOWN STREETSCAPE IMPROVEMENTS
The purpose of this project is to make selective improvements to the following areas within the downtown business district; Center Street, American Legion Drive, Main Street, Hoosic River Bridge, Holden Street, Eagle Street (Main Street to Church Street), Route 2, Marshall Street, Eagle Street (Route 2 to Hoosic River) and River Street. The Improvements include: pavement overlays, minor drainage improvements, sidewalk and ramp accessibility Improvements, decorative pavement treatments adjacent to sidewalks, and landscaping. This project will also provide major improvements to five of the traffic signals: State St/ Main Street, Main Street/American Legion Drive, Marshall Street/Anthony's Drive, Main Street/Ashland Street and Marshall Street/River Road Intersections.
Location:
  • City of North Adams
  • Resident Engineer: Peter Lamarre
    Construction Contract Value: $2,480,078.00
    Construction Bid Price: $2,196,798.64
    Initial Construction Estimate: $2,436,317.97
    District: District 1

    Contracts (1) Progress
    # 62026 -- Construction Contract
    Downtown Streetscape Improvements and Related Work. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/04/2007
    Project Initiation Form PIF Entered 12/05/2007
    Project Initiation Form PRC Submitted 12/05/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Review Committee Letter 02/19/2008
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 08/25/2009
    100% Design 100% Package Comments to DE 09/01/2009
    25% Design 25% Package Received 10/30/2008
    25% Design 25% Package Comments to DE 12/26/2008
    25% Design Design Public Hearing 03/23/2009
    75% Design 75% Package Received 08/04/2009
    75% Design 75% Package Comments to DE 08/24/2009
    Final Design PS&E Received 09/28/2009
    Final Design PS&E to FAPRO 09/15/2009