| Project Description: |
WESTBOROUGH- BRIDGE PRESERVATION, W-24-026, LYONS STREET OVER STATE ROUTE 9 (TURNPIKE ROAD)
The scope of the work for the bridge carrying Lyons Street over Route 9 includes repairing deck joints; replacing the wearing surface; replacing anchors at bridge bearings; painting the structural steel; and performing concrete repairs on the substructure, wingwalls and abutments.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Hemendra Bhatt![]() |
| Estimated Total Contract Cost: | $860,621.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|